Time Intervals
Previous 10 Events
| Operation | Event | Description | End Date | |
|---|---|---|---|---|
| 1 | Run Casing | Casing Problem | Laid out joint 162 due to damaged coupling. | Tue Nov 2020 14:12:00 |
| 2 | Run Casing | Main Step | Run 166 joints of 7" 23# K55 BTC casing. | Tue Nov 2020 11:12:00 |
| 3 | Reaming | Main Step | Mon Nov 2020 21:42:00 | |
| 4 | Drill Actual | Hole Deviation | Tight hole, considering diviation | Mon Nov 2020 21:12:00 |
| 5 | Drill Actual | Main Step | Continue drilling to 3109m | Mon Nov 2020 16:12:00 |
| 6 | Drill Actual | Equipment Problem | Equipment problems resolved. | Mon Nov 2020 11:42:00 |
| 7 | BHA Trip Out | Main Step | POOH BHA, L/D tools | Mon Nov 2020 01:42:00 |
| 8 | Drill Actual | Main Step | Drill ahead with 8 1/2" hole to 2890 m. | Sun Nov 2020 17:42:00 |
| 9 | Rig Service | Main Step | Performed Rig service | Wed Nov 2020 15:42:00 |
| 10 | Cut Off Drilling Line | Main Step | Wed Nov 2020 15:00:00 |